London tube details radical procurement strategy

Note* - All images used are for editorial and illustrative purposes only and may not originate from the original news provider or associated company.

Subscribe

- Never miss a story with notifications

- Gain full access to our premium content

- Browse free from any location or device.

Media Packs

Expand Your Reach With Our Customized Solutions Empowering Your Campaigns To Maximize Your Reach & Drive Real Results!

– Access the Media Pack Now

– Book a Conference Call

Leave Message for Us to Get Back

Related stories

Lifecycle Focused Construction Practices for Sustainable Infrastructure

Sustainable infrastructure development requires extending construction thinking beyond initial project completion to encompass the entire building lifecycle spanning decades of operation, maintenance, and eventual decommissioning. By integrating lifecycle cost analysis, selecting durable materials, designing for operational efficiency, planning for maintenance accessibility, and anticipating end-of-life material recovery, construction professionals create assets that deliver long-term value while minimizing environmental impact. This holistic approach transforms infrastructure from cost centers requiring perpetual maintenance into resilient assets that serve communities sustainably across generations.

Improving Construction Efficiency Without Compromising Quality

Achieving construction efficiency requires process-focused improvements that enhance productivity while maintaining or improving quality standards. Through workflow optimization, enhanced coordination mechanisms, quality management practices, and strategic technology integration, construction organizations deliver projects faster and more cost-effectively without sacrificing structural integrity or compliance. Balancing speed with excellence transforms construction management from a trade-off exercise into a synergistic approach where efficiency and quality reinforce one another.

Managing Material Costs in a Volatile Construction Market

Construction material price volatility presents significant challenges to project budgeting and risk management. Strategic procurement approaches, supply chain resilience strategies, and contract mechanisms that balance risk effectively enable stakeholders to navigate market fluctuations successfully. Understanding market dynamics, implementing escalation clauses, developing flexible procurement strategies, and maintaining strong supplier relationships help construction professionals maintain project viability despite unpredictable material cost movements.
- Advertisement -
Achema Middleeast

London Underground to bypass main contractors and take on more construction risk in £331m station programme.

London Underground will take on a much higher proportion of construction risk under its radical new approach to procuring work that will see it bypass main contractors.

Speaking to Building this week, Miles Ashley, programme director of Crossrail and stations at London Underground, said London Underground’s new approach, which involves bypassing tier one contractors and entering into direct relationships with trade contractors, will lead to the client taking on a much greater level of construction risk.

He said: “Historically we have tended to contract in these long chains. The public sector tends towards these arrangements because it’s very low risk.

“If we are going to access better outcomes in terms of value, we are going to have to take more risk.”

Last month, Building revealed London Underground was in the process of setting up the new system that will mean engaging directly with lower levels of the supply chain on its seven-year £331m station upgrade programme.

Ashley said the delivery partner would run the £331m programme of works across 71 stations and assist London Underground with all its construction work. It will also help develop skills in construction management, construction planning and commercial management.

London Underground expects to achieve cost savings of at least 12% and up to 25% through the Stake system with contractors due to be appointed between September and the end of this year.

Ashley said he wanted to restore “a sense of craftsmanship to the workplace” and that contractors with tradespeople directly on their books would be at an advantage in bidding for work on the seven-year programme.

“The question we are going to be asking is what people have you got? It’s going to favour people who can bring us that capability,” he said.

“If we can get a capable, incentivised, engaged and consistent workforce at that [tradespeople] level and then build the rest of the system around that, then we can get a good result.”

Suzannah Nichol, chief executive of the National Specialist Contractors Council, said major clients were questioning the value they were getting from main contractors.

Achema Middleeast

Latest stories

Related stories

Lifecycle Focused Construction Practices for Sustainable Infrastructure

Sustainable infrastructure development requires extending construction thinking beyond initial project completion to encompass the entire building lifecycle spanning decades of operation, maintenance, and eventual decommissioning. By integrating lifecycle cost analysis, selecting durable materials, designing for operational efficiency, planning for maintenance accessibility, and anticipating end-of-life material recovery, construction professionals create assets that deliver long-term value while minimizing environmental impact. This holistic approach transforms infrastructure from cost centers requiring perpetual maintenance into resilient assets that serve communities sustainably across generations.

Improving Construction Efficiency Without Compromising Quality

Achieving construction efficiency requires process-focused improvements that enhance productivity while maintaining or improving quality standards. Through workflow optimization, enhanced coordination mechanisms, quality management practices, and strategic technology integration, construction organizations deliver projects faster and more cost-effectively without sacrificing structural integrity or compliance. Balancing speed with excellence transforms construction management from a trade-off exercise into a synergistic approach where efficiency and quality reinforce one another.

Managing Material Costs in a Volatile Construction Market

Construction material price volatility presents significant challenges to project budgeting and risk management. Strategic procurement approaches, supply chain resilience strategies, and contract mechanisms that balance risk effectively enable stakeholders to navigate market fluctuations successfully. Understanding market dynamics, implementing escalation clauses, developing flexible procurement strategies, and maintaining strong supplier relationships help construction professionals maintain project viability despite unpredictable material cost movements.

Cost Optimization Strategies in Material Intensive Construction Projects

Material-intensive construction projects require comprehensive cost optimization strategies that balance budget control with quality maintenance. Through systematic planning, prefabrication techniques, lean construction principles, and strategic procurement approaches, contractors can significantly reduce project expenses while maintaining structural performance standards. Effective material efficiency combined with process optimization transforms how organizations deliver complex construction projects.

Subscribe

- Never miss a story with notifications

- Gain full access to our premium content

- Browse free from any location or device.

Media Packs

Expand Your Reach With Our Customized Solutions Empowering Your Campaigns To Maximize Your Reach & Drive Real Results!

– Access the Media Pack Now

– Book a Conference Call

Leave Message for Us to Get Back

Translate »