Mersey bridge project reaches landmark with temporary structure completed

Note* - All images used are for editorial and illustrative purposes only and may not originate from the original news provider or associated company.

Subscribe

- Never miss a story with notifications

- Gain full access to our premium content

- Browse free from any location or device.

Media Packs

Expand Your Reach With Our Customized Solutions Empowering Your Campaigns To Maximize Your Reach & Drive Real Results!

– Access the Media Pack Now

– Book a Conference Call

Leave Message for Us to Get Back

Related stories

A Guide to Indoor Playgrounds for Amusement Parks

Today’s amusement parks have become all-season attractions for large...

Aqua-G EVO Debut Strengthens Panasonic HVAC Portfolio Range

Panasonic has introduced a new propane-based heat pump aimed...

Top Commercial Roofing Companies Serving the Orlando Area

The right commercial roofing company in Orlando must do...
- Advertisement -

The first bridge over the Mersey for 54 years has been completed as part of the construction of the new Mersey Gateway crossing.

Merseylink construction workers Thomas Duncalf, left, and Asa Humphrey on the newly completed trestle bridge

The Merseylink construction consortium of FCC, Kier and Samsung C&T, which is building the £600m crossing for Halton Borough Council, has completed the trestle bridge – a temporary bridge that will act as an access platform for construction teams to work from when building the new structure.

It is the first bridge to be built over the River Mersey in Halton since 1961, when the nearby Silver Jubilee Bridge was opened.

The trestle bridge is used by construction vehicles but is not open to public traffic. A lifting section, which can be raised to allow boats to pass, will be installed shortly.

Merseylink project director Richard Walker said: “Completion of the trestle bridge marks another important milestone for the Mersey Gateway project. It will provide us with full access to the river, enabling work to start on the central cofferdam.”

The trestle bridge will be dismantled and removed completely when the new Mersey Gateway Bridge is in place, expected to be in 2017.

Thomas Duncalf, from Runcorn, was one of the first workers to walk across the new trestle bridge. He said: “I’m excited to be working on the project. It’s a great opportunity. My grandad worked on the Silver Jubilee Bridge and it’s an important part of my family history. I feel honoured to be part of the team building the new Mersey Gateway bridge.”

Achema Middleeast

Latest stories

Related stories

A Guide to Indoor Playgrounds for Amusement Parks

Today’s amusement parks have become all-season attractions for large...

Aqua-G EVO Debut Strengthens Panasonic HVAC Portfolio Range

Panasonic has introduced a new propane-based heat pump aimed...

Top Commercial Roofing Companies Serving the Orlando Area

The right commercial roofing company in Orlando must do...

Emergency Garage Door Repair Companies in Colorado

Dealing with a stuck garage door or a broken...

Subscribe

- Never miss a story with notifications

- Gain full access to our premium content

- Browse free from any location or device.

Media Packs

Expand Your Reach With Our Customized Solutions Empowering Your Campaigns To Maximize Your Reach & Drive Real Results!

– Access the Media Pack Now

– Book a Conference Call

Leave Message for Us to Get Back

Translate »