The Kane Group, a specialist in mechanical and electrical systems, has officially secured a £40m subcontract for the redevelopment of the former John Lewis headquarters located at 171 Victoria Street in central London. The wider project, valued at £135m, involves the refurbishment and extension of the site for the client, Kirkglade. The 171 Victoria Street project is being delivered by Sisk and is currently scheduled to reach completion in the final quarter of 2027.
Technical Scope and Design Strategy
The design, led by the architect TP Bennett, aims to provide over 18,500 square metres of Grade A office space. As part of the 171 Victoria Street project, the Kane Group will deliver a comprehensive design-and-build mechanical and electrical package. A primary goal of this contract is the complete upgrade of building services to facilitate all-electric office accommodation.
To ensure the continuity of local business, the contractor will carry out these complex works while the ground-floor retail units remain fully operational. To streamline the construction programme and minimize site disruption, the Kane Group plans to utilize prefabricated building services components, produced at its own offsite facility. The company recently expanded this facility by 1,900 square metres to bolster its manufacturing capacity.
Sustainability and Retrofit Integration
The refurbishment aligns with the retrofit-first strategy established by Westminster Council. This approach emphasizes the reuse or recycling of materials recovered during the partial deconstruction phase, including existing glazing units, concrete, steelwork, and 500 stainless steel window frames.
The redevelopment will also feature a trapezoidal facade utilizing low-carbon Orae glass, which is intended to reduce the carbon impact of the glazing by 40 per cent compared to standard alternatives. Furthermore, Sisk and Kirkglade have partnered with London Structures Lab to incorporate Ecocem-ACT low-carbon concrete throughout the site.
Sisk’s UK managing director, Ger Hayes, noted the team’s familiarity with these materials from previous applications. Regarding the integration of low-carbon concrete, Hayes said: “We are very confident that all the required performance standards will go hand in hand with significantly reducing carbon in the building.”
Company Growth and Industry Context
This contract follows a milestone for the specialist contractor, which recently reported exceeding its £100m turnover target for 2026. According to the firm, this project strengthens its existing partnership with Sisk. Previous collaborative efforts by the Kane Group include high-profile work at Claridge’s Hotel, Wood Wharf in London, and Trinity by Breakthrough in Oxford. With the focus shifting toward all-electric office environments and sustainable refurbishment practices, the company continues to play a significant role in the London construction sector.