Final pod placed on World’s tallest modular resi tower

Note* - All images used are for editorial and illustrative purposes only and may not originate from the original news provider or associated company.

Subscribe

- Never miss a story with notifications

- Gain full access to our premium content

- Browse free from any location or device.

Media Packs

Expand Your Reach With Our Customized Solutions Empowering Your Campaigns To Maximize Your Reach & Drive Real Results!

– Access the Media Pack Now

– Book a Conference Call

Leave Message for Us to Get Back

Related stories

Holcim ECOPlanet to Advance Sustainable Construction in UAE

Holcim has officially introduced its ECOPlanet low-carbon cement range...

What Is House Recladding and Does Your Home Really Need It?

If you have been noticing cracks in your exterior...

NESL, Casilio Deal Expands Lehigh Valley Concrete Network

New Enterprise Stone & Lime Co., Inc. has completed...
- Advertisement -

Tide Construction has craned the final pod into place on the world’s tallest modular building in Croydon.

The last of 1,526 modules have been assembled on site in south London to create two towers measuring 44-storeys and 38-storeys.

The 136m scheme is as high as the London Eye and will house 546 Build to Rent homes.

Tide and and its offsite division Vision Modular Systems will complete the project in just over two years – half the time it would have taken using traditional methods of construction.

Christy Hayes, CEO of Tide Construction, said: “Construction of the towers began in February 2018 after planning consent was gained back in November 2017.

“From there, the 1,526 modules were stacked on top of a concrete podium linking both towers at ground floor level.

“Once the concrete cores of the two towers were complete, Vision Modular Systems’ pre-fitted, pre-plumbed and pre-wired modules began arriving on site.

“We successfully installed the last module in just 35 weeks – three weeks ahead of an already tight schedule – after the first was craned into place.

“As we reach this exciting milestone, already 80% of the glazed terracotta façade has also been completed.”

Achema Middleeast

Latest stories

Related stories

Holcim ECOPlanet to Advance Sustainable Construction in UAE

Holcim has officially introduced its ECOPlanet low-carbon cement range...

What Is House Recladding and Does Your Home Really Need It?

If you have been noticing cracks in your exterior...

NESL, Casilio Deal Expands Lehigh Valley Concrete Network

New Enterprise Stone & Lime Co., Inc. has completed...

Best Construction Project Scheduling Tools with Real-Time Updates

Most construction schedules fall apart not because the plan...

Subscribe

- Never miss a story with notifications

- Gain full access to our premium content

- Browse free from any location or device.

Media Packs

Expand Your Reach With Our Customized Solutions Empowering Your Campaigns To Maximize Your Reach & Drive Real Results!

– Access the Media Pack Now

– Book a Conference Call

Leave Message for Us to Get Back

Translate »